Working principle of Liugong excavator and main relief valve

Posted on:       View:1184

                 

                                                               One-way overload valve

9_20200224175835.jpg

Over-opening valve opening dynamics

9_20200224175955.jpg

Check valve open

9_20200224180112.jpg

Principle of one-way overload valve

1.Overflow function

9_20200224180430.jpg

When the oil pressure rises to the preset pressure of the spring B, the spool (A) opens: the oil bypasses the spool A through the (C) side hole: it flows to the (E) channel.

9_20200224180539.jpg

The oil flow creates a pressure drop before and after the hole (J): the piston (H) is moved to the right and sits on the top of the spool (A).

9_20200224180621.jpg

The hydraulic oil flows from (1) chamber through (A) the top throat of the spool into the (2) chamber: then bypasses (A) the spool through the (C) side hole and flows into the (E) channel.
As the pressure at the throat K decreases, the pressure in the chamber (1) x d1 cross-sectional area> (2) the pressure in the chamber x d2 cross-sectional area, the valve core (C) is pushed away and the oil flows into the low-pressure channel.

2.compensation function
Prevent cavitation in the hydraulic oil circuit during work or when unexpected forces act on the machine.

9_20200224180817.jpg

The pressure of the oil cylinder is usually higher than the pressure of the oil tank, and d3 <d4. Therefore, the poppet valve F will not 

move.

9_20200224180957.jpg


When the cylinder port pressure drops below the tank pressure, the valve core F is opened due to the area of d3 and d4, and the hydraulic oil flows from the tank oil passage to the cylinder port to avoid the occurrence of cavitation